Commercial millwork quote comparison checklist

Before awarding a millwork package, check that each bidder priced the same drawings, materials, hardware and installation scope. Ask the bidder to confirm any missing cost in writing.

What to check in each bid

Drawings and quantities
Check the revision date, addenda, rooms, cabinet counts and quantities. Confirm who measures the site, prepares shop drawings and covers a second field visit.
Materials and hardware
Match the substrate, exposed finishes, edge treatment and hardware specification. Flag allowances and substitutions. Ask whether they are included in the quoted total.
Delivery and installation
Define who unloads, moves material to the room, installs it and completes touch-ups. Confirm access, staging, storage and any required after-hours labor.
Schedule and terms
Check the lead time trigger, quote expiry, deposit and payment milestones. Record exclusions, warranty responsibilities and which scope changes require a revised quote.

Compare the same delivered and installed scope

In this fictional Canadian-dollar example, Quote B has a lower base price. Once its delivery and installation are included, Quote A costs CA$600 less.

One package in CAD, before applicable tax
CostQuote AQuote B
Quoted package$12,400$11,900
Delivery included above or addedIncluded$350
Installation included above or addedIncluded$750
Comparable total$12,400$13,000

Leave unpriced work marked as unknown. For freight, duty or imported hardware, use the landed cost guide to put both quotes on the same basis.