Commercial millwork quote comparison checklist
Before awarding a millwork package, check that each bidder priced the same drawings, materials, hardware and installation scope. Ask the bidder to confirm any missing cost in writing.
What to check in each bid
- Drawings and quantities
- Check the revision date, addenda, rooms, cabinet counts and quantities. Confirm who measures the site, prepares shop drawings and covers a second field visit.
- Materials and hardware
- Match the substrate, exposed finishes, edge treatment and hardware specification. Flag allowances and substitutions. Ask whether they are included in the quoted total.
- Delivery and installation
- Define who unloads, moves material to the room, installs it and completes touch-ups. Confirm access, staging, storage and any required after-hours labor.
- Schedule and terms
- Check the lead time trigger, quote expiry, deposit and payment milestones. Record exclusions, warranty responsibilities and which scope changes require a revised quote.
Compare the same delivered and installed scope
In this fictional Canadian-dollar example, Quote B has a lower base price. Once its delivery and installation are included, Quote A costs CA$600 less.
| Cost | Quote A | Quote B |
|---|---|---|
| Quoted package | $12,400 | $11,900 |
| Delivery included above or added | Included | $350 |
| Installation included above or added | Included | $750 |
| Comparable total | $12,400 | $13,000 |
Leave unpriced work marked as unknown. For freight, duty or imported hardware, use the landed cost guide to put both quotes on the same basis.
Get a second set of eyes before you award
AlmaRumo reviews up to two supplier quotes for one commercial millwork package. We identify scope and cost differences and give you questions to take back to the suppliers. CA$249 plus applicable tax, with scope and timing confirmed before payment.
Request a quote review