Procurement guide
How to calculate landed cost and compare supplier quotes
Landed cost is the cost of bringing goods to an agreed destination. Start with the price of the goods, add the costs required to reach that destination, and divide by the units you expect to accept.
Put both quotes on the same basis
- Match the scope. Compare equivalent materials and specifications. Agree on a delivery point, a scope for final delivery or installation, and a way to count accepted units.
- Convert to one currency. Use the same comparison currency and record the exchange rate, date, and source for each conversion.
- Assign the costs. Check who pays for packing, freight, insurance, duties, brokerage, delivery and inspection. Count a cost once when it is already included elsewhere. Identify costs that are still unknown.
- Compare per accepted unit. Divide the comparable total by the number of accepted units. Show recoverable taxes separately when estimating cash outlay. Include installation on both sides when the decision covers installed cost.
Comparable cost per accepted unit = comparable total ÷ accepted units
Worked supplier quote comparison
These are fictional estimates for 100 accepted units in each quote, delivered to the same location. Other costs are assumed included or inapplicable. All amounts are in Canadian dollars.
| Cost | Quote A | Quote B |
|---|---|---|
| Goods | $15,000 | $14,000 |
| Freight and delivery | $2,500 | $3,000 |
| Duty and brokerage | $500 | $1,500 |
| Comparable total | $18,000 | $18,500 |
| Cost per accepted unit | $180.00 | $185.00 |
Quote B starts $1,000 lower on goods. Its added costs bring the comparable total $500 higher, or $5 per accepted unit.
Check your import assumptions
For Canadian imports, duty and tax depend on factors such as tariff classification, origin, and value for duty. If you are waiting on a freight or brokerage figure, mark the comparison incomplete until you have a supportable estimate. Canada Border Services Agency guide to importing commercial goods